Westminster
Street Reconstruction
Kerrville, Tx
PLEASE SEE CONSTRUCTION UPDATES BELOW
Phase 1
First St. to E. Main St.
All Concrete installation has been completed. Our crews have began installing Top Soil and Sod. Street Crews will prep the Flex Base for paving. Asphalt Paving is scheduled for 11/15 - 11/22.
Phase 2
E. Main St. to Lang Dr.
Remaining sections of Concrete are to be completed by 11/13. Once completed, Top Soil and Sod installation will follow. Asphalt Paving is scheduled for 11/15 - 11/22.
Road will be closed to through traffic during construction.
Please refrain form parking vehicles in the roadway during regular business hours (7am to 5pm) Monday - Friday.
We will make every effort to accommodate local residents access to their driveways and maintain all-weather surface during street construction.
For Immediate Assistance, Please Contact:
Site Superintendent - Bryan Judd (210) 439 - 7692
Project Manager - Gerald McLeod (830) 358 - 9206